Cut or drilling schedule
Mark each opening, penetration, joint or removal area and include length, width, diameter, depth, angle, quantity and orientation.
Quote-ready concrete cutting scope
A useful concrete-cutting quote starts with the required result and the site information needed to plan it. Send the opening, penetration, joint or removal layout together with dimensions, material, access, known services, structural responsibility and required timing.
Cutcore can review residential, commercial, industrial and civil enquiries across Brisbane and South East Queensland. Availability, method, duration and price remain project-specific; a phone discussion or online form is the start of scoping, not a guarantee of same-day attendance or a final fixed price.
Planning framework
Mark each opening, penetration, joint or removal area and include length, width, diameter, depth, angle, quantity and orientation.
Provide current drawings, approvals, reinforcement or post-tensioning information, service plans, scans, isolations and the responsible project contacts.
Explain equipment routes, working height, traffic, occupancy, neighbours, work hours, power, water, ventilation and protection requirements.
Assign support, lifting, cut-section or core handling, slurry capture, loading, disposal, cleanup, reinstatement and acceptance responsibilities.
Scope and responsibility
The quote should identify the proposed method, quantities, mobilisation, preparation, work-zone controls, water or dust approach, support and lifting assumptions, removal and disposal scope, timing, GST treatment, provisional items and the process for changed conditions. Compare competing quotes only after the scopes are aligned.
Cutcore does not use a quote request to approve a structural change or guarantee concealed services are clear. The responsible engineer, designer, asset owner, principal contractor or service authority may need to approve or supply information before the cutting method and sequence are finalised. Scanning can inform the work but cannot guarantee every embedded item is found.
Before you request a quote
Photos and marked-up drawings can support an initial review. A site inspection or more information may still be required where access, material, services, structure or hidden conditions are uncertain.
Do not assume same-day attendance. Share the location, approved scope, site readiness and timing so current availability and prerequisites can be checked.
Only if stated. Confirm scanning, service investigation, slurry, cores, cut sections, loading, disposal, cleanup and reinstatement in the written inclusions.
Stop and review material changes before continuing. The quote should explain provisional items, exclusions and how added work or changed conditions will be assessed and approved.
Discuss the project
The team can review the information and identify what else is needed for a project-specific quote.
Privacy settings
This checklist helps you prepare a clear first discussion. It does not set the cutting method. It does not replace engineering, service locating, permits, site rules or a task risk review. Start with the facts you know. Mark the facts that still need a competent person.
Write one sentence about the finished result. Say what must be cut, drilled, scanned, ground or removed. Add the reason for the work. State what must stay in place. Mark the start and end points. If a drawing controls the work, name its number and revision.
Use dimensions that can be checked. Add the opening width and height. Add the cut length or hole diameter. Note the likely depth. State whether the work is in a slab, wall, beam, pavement or another element. Do not guess if the structure is not known. Record that gap.
Draw the work area. Mark the street, gate and entry path. Show stairs, lifts and narrow turns. Add the work face. Mark occupied rooms and public areas. Show where people and vehicles move. Add the closest practical load point. Keep the map with the photos.
Walk the access path before the call. Measure tight doors and gates. Note soft ground, steep grades and low clearances. State if the work is above or below ground. Say whether normal site activity must continue. Access can affect the method, setup and safe work area.
Take one wide photo of the whole work zone. Then take close photos of each marked cut or hole. Put a tape, rule or known object in the frame for scale. Photograph both sides of a wall or slab when access allows. Name each file by area and date.
Photos are a starting point. They do not prove what is inside concrete. They do not confirm structural approval. Add current drawings and service information where they exist. Tell the reviewer when a photo is old or when the site has changed since it was taken.
Say whether the concrete is new or existing. Note visible cracks, patches, joints and coatings. Record known reinforcement or post-tensioning information. Add the responsible engineer or designer when structural work is involved. Do not treat an old drawing as verified without the right review.
Mark any part that must be supported before a cut is complete. Think about the weight and shape of each released section. State who owns the support, lifting, removal and disposal plan. These items need agreement before work starts. They should not be left as an on-site surprise.
Gather current service drawings and site records. Mark known power, water, gas, data, fire and drainage routes. Use the relevant locating process for the site. Scanning can add useful information, but it cannot promise that every hidden item will be found. Keep that limit in the plan.
State who will review scan results and approve the marked work. Add any exclusion zone around a found item. Record the next step if information conflicts. A clear hold point lets the team pause before a cut or hole crosses an uncertain area.
Say whether the area is inside or outside. Note nearby homes, shops, offices, patients, students or site workers. Add any site limit for noise, water, dust, vibration or work hours. State who sets each limit. Share building rules and induction needs before the work date.
Concrete processing can create respirable crystalline silica. The work plan should follow current Queensland requirements and the site risk controls. Do not rely on a broad web statement for a task-specific control. The responsible parties should set the method, equipment, isolation and protective measures.
Confirm whether water is available and where it may be used. Mark drains and sensitive finishes. State how slurry, dust and loose material will be contained. Add the waste route and disposal responsibility. Protect nearby areas before work starts. Do not assume runoff can enter a drain.
List finishes that must stay clean. Add walls, glazing, ceilings, equipment and occupied rooms. State who moves loose items. Note any wet work that must happen first. Give fresh paint, flooring and joinery enough separation from cutting or removal work.
Write the earliest access time and the required handover time. Add site opening hours. Note deliveries, traffic peaks and other trades. State whether the area can close. If it must stay partly open, mark the route that remains available and the person who approves the arrangement.
Ask about setup, work, clean-up and handover as separate stages. Avoid a timing promise before the scope and constraints are reviewed. A small change in access, depth, reinforcement or section handling can alter the sequence. Keep room in the program for new site facts.
Give each contractor the same brief. Use the same drawing revision and dimensions. Ask what is included for setup, scanning, cutting, supports, lifting, removal, protection and clean-up. Note the assumptions in each price. Compare the written scope, not only the total.
Ask what information is still missing. Ask which party must provide it. Record items that may change cost or timing. State how a change will be raised and approved. Keep the final quote, scope and attachments together so the site team can use one current record.
Check that the approved marks are still visible. Confirm access, keys and inductions. Move loose goods as agreed. Tell affected people about the work zone. Check that the responsible site contact can be reached. Share any change in the structure, services, program or nearby activity.
Use a short pre-start walk. Match the site to the brief. Check each marked location. Review access and exclusion areas. Confirm the change process. If a key fact is not clear, pause that part. A short pause is better than carrying an unchecked assumption into the work.
Name each area in the same way on the drawing, photos and notes. Record agreed changes. Add the date and the person who approved them. Keep scan markings and hold-point records with the job file. Take progress photos where the site rules allow.
At handover, walk the work area in good light. Check the agreed openings, edges and removal area. Note any item that still needs attention. Confirm clean-up and waste responsibilities. Record when barriers or supports may change. Ask the responsible party before removing a control.
Put the job name and suburb at the top. Add one current site contact. State the finished result in one line. List the dimensions below it. Add the drawing revision, photo file names and known service information. Mark the work face and access path. Note the required work window. Keep open questions in a separate list so they cannot be mistaken for confirmed facts.
Give each open question an owner. The engineer may need to confirm a structural point. The site team may need to confirm access or isolation. A locator may need to review a marked area. The client may need to choose a finish or disposal option. Add a due date where it helps. Update the brief when an answer arrives, and keep the old version out of the active site file.
Use plain labels. Write “wall opening” instead of an internal nickname. Write the actual floor or room. Add north, south, east or west when two areas look alike. Keep dimensions in one unit. Show whether a depth is confirmed or estimated. A short, consistent brief reduces avoidable questions and gives every party the same starting point.
Start with the suburb and site type. Add the required result, dimensions and material. Attach the plan and clear photos. Note access, services, occupied areas and preferred timing. List the approvals already held. Mark each open question. This gives the first review a practical base.
You can review the Cutcore quote-planning page, then send the project details to Cutcore. For a broader overview, compare the concrete cutting enquiry guide and the service directory.
Pick one lead for the job. Give that person the full file. Add the site map. Add the cut list. Add clear photos. Add the key dates. List all site rules. Share the same file with each firm. This helps each quote start with the same facts.
Keep the file small. Use one live copy. Name the old copies as old. Do not leave two plans with the same name. Add the date to each new plan. Tell the site team when a file has changed. A clear file can stop an old mark from being used.
Start at the road. Walk to the gate. Walk to the load point. Walk to the work face. Check each turn. Check each step. Check each door. Look up for low pipes and beams. Look down for soft ground and trip points. Write each limit on the site map.
Walk the same path back out. Think about tools and waste. Think about a cut piece that may be hard to move. Mark the path that staff will use. Mark the path that guests will use. Keep those paths apart from the work zone where the site plan allows.
Use names such as north wall, bay two or ground floor east. Put the same name on the plan. Put it on the cut list. Put it in each photo name. Use it in site notes. This makes a short call much more clear. It also helps the next shift find the right place.
Do not use a name that only one trade knows. Avoid words such as here, there or the old spot. Add a room, grid or floor. Add a side of the wall. Show an arrow on the plan. A plain label can stop work from being set out on the wrong face.
Mark each hole and cut in a clear way. Add a number. Add the size. Add the depth if it is known. Add the side of the work. Put the same number on the list. Do not write over an old mark. Remove or cross out a mark that no longer forms part of the work.
Check marks in good light. Read them from the place where the work will start. Ask the site lead to check the plan. Ask the right design party to approve work that can change the structure. Keep proof of each key check with the job file.
Take a wide shot first. Show the whole area. Take a mid shot next. Show the mark and its place. Take a close shot last. Show the size and surface. Put a tape in the close shot. Use the same area name in all three file names.
Add the date. Add a note if the mark is not final. Show both faces of a wall when you can reach them. Show the space below a slab when it can be seen. Keep raw files. Do not crop out a fact that helps show the site or the access limit.
A plan can be old. A wall can move. A service can be added. A room name can change. Check the plan on site. Note each gap. Do not make the plan fit by guess. Raise the gap with the person who owns the plan. Wait for a clear answer where the gap may change the work.
Write the plan number on the brief. Add its date. Add the page that shows the work. If a sketch is used, state who made it. State who checked it. Keep the sketch with the main plan. Do not let a loose screen shot become the only site guide.
Concrete can hide bars, wires, pipes and voids. Site records may help. A scan may help. A scan has limits. No one broad step can prove that every hidden item is found. Mark what is known. Mark what is not known. Set a stop point for any new or unclear sign.
Ask who will read the scan. Ask who will clear the mark. Add a safe gap where the site plan calls for one. Keep the marks dry and clear. If a mark is lost, do not guess its old place. Raise the issue. Check the area again before the cut or hole starts.
Show the work zone on the map. Add room for the tool and the person who will use it. Add a path for cords and hoses. Add a place for water and waste. Add a place for each cut piece. Keep doors and fire paths in view. Ask the site lead to approve the zone.
Tell staff which path is shut. Put signs in the right place. Keep kids and pets away. Keep guests out of the zone. Check the zone at each new shift. Fix a trip point at once. Move waste before it blocks the path. Keep light on the marks and the work face.
A cut can free a heavy part. Work out its size and likely weight. State how it will be held. State how it will be moved. State where it will go. Check the load path. Keep people out from below or beside it. Use the plan set by the right site and design parties.
Do not wait for the last edge to talk about the piece. Put the lift and support step in the scope. Add the owner of each task. Check the gear path. Check the set-down point. Stop if the real part does not match the plan. Raise the change before the cut goes on.
Find the water point. Check who may use it. Mark each drain. Keep run-off out of a place where it does not belong. Set the way slurry will be caught. Set the waste path. Protect walls and goods near the work. Tell the team if the area must stay dry.
Dry dust can harm health. Wet work can add slip and run-off risk. The job plan must use the right site controls. Follow the current rules and the task review. Check the controls through the shift. Stop and fix a failed control. Do not let a short job skip a key step.
State the first time work may start. State the last time it may run. Add any quiet time. Note homes, shops, care rooms and work areas near the site. Tell the team about a test, class or meet that needs less noise. Keep the site contact phone close.
Do not promise a finish time from a photo alone. Setup takes time. Checks take time. Clean-up takes time. A new site fact can change the plan. Add a fair work window. Tell other trades what may close. Leave a gap before the next task where the site needs one.
Meet at the work face. Read the area name. Check the mark. Check the plan. Check the service note. Check the access path. Check the work zone. Check the cut piece plan. Name the site lead. Name the person who may approve a change. Keep the talk tied to the real job.
Ask one simple question: what has changed? A door may be shut. A trade may be in the way. A mark may be lost. A new pipe may be in view. The weather may affect the area. Write down the change. Fix the plan before that part of the work begins.
Stop the part that has changed. Take a clear photo. Mark the place on the map. Write one short note. Add the time. State why the old plan no longer fits. Send it to the right person. Ask for a clear yes, no or new step. Keep the answer with the file.
Do not hide a cost or time effect. State it before the new task starts. Check who may approve it. Put the new size or method in the scope. Share the change with the site team. Remove the old mark if it could cause doubt. Use the new plan from then on.
Look at each area in good light. Note what is done. Note what is still open. Check the work zone. Check each cut piece. Move loose waste. Keep paths clear. Take one wide photo. Add close shots where they help. Name the files by area and date.
Tell the next shift about each hold point. Show them the live plan. Show them any new mark. Do not rely on a quick word at the gate. Put the key facts in the note. A short written handover helps the next person start with less doubt.
Use the cut list for the walk. Check each number. Check each size. Look at edges and the work face. Note any part that needs a talk. Check the agreed clean-up. Check that waste has gone to the right place. Keep guards and supports until the right party clears them.
Save the final plan. Save the change notes. Save the scan and mark records. Save the final photos. Add the work date. Add the handover contact. Give the site team the parts they need. A small, clear file can help when the next trade starts or when a later question is raised.
Keep the final record with the site plan. Mark the new hole or opening. Note a part that was moved or changed. Tell the asset owner what the file shows. Do not claim the file shows more than it does. Keep a clear note of each limit and each fact that was not checked.
Review the file before more work starts in the same area. The old photos may help, but the site may have changed. Walk the place again. Check the marks again. Use the last file as a lead, not as proof. Start the next task with a fresh site check.